Interlock House

Download Adobe Flash

Adobe Flash is required to view the videos on this page. If you do not have Adobe Flash you can download a free copy from Adobe. If you already have Adobe Flash Player installed, you must also enable JavaScript.

Adobe Flash Video

  • Assembly Demo: Demonstration of how the Interlock House is assembled.
  • Feb 2nd-6th: Warmboard installation and roof framing.
  • Feb 9th-13th: Roof module assembly.
  • Feb 16th-20th: Roof assembly continues.
  • Feb 23rd-27th: Completion of roof modules.
  • March 2nd-6th: Moving roof modules from the warehouse, wall framing.
  • March 9th-13th: Wall assemblies are put into place.
  • March 23rd-27th: Moving lower modules from the warehouse.
  • Module Lift: Lifting roof modules on top of the lower modules.
  • Apr 27th-May 1st: Finals Week. Very little activity.
  • May 18th-21st: Biobased Insulation and roof sheathing.
  • Jun 29th-Jul 3rd: Roofing and interior work.

This presentation contains no sound.